• Concrete Project

Loading Dock Restoration

Back to all projects

Project details

Company

Hines Canada Management

Service

Loading Dock Membrane Installation

Industry

Property Management

Materials

MasterSeal 2500

 

 

This loading dock membrane re & re project could not have gone better.  For many of our clients down time is not an option, and Gator’s ability to be flexible is key to the success of such projects.   In order to keep the loading dock fully operational during the repairs and surface preparation, all preparation work was completed between 6:00 pm and 6:00 am.  When it came time for the coating installation, the entire coating was done with seamless installation over 2 days to meet the aesthetic criteria of the client.  20,000 square feet of installation in 2 days!  We were also able to partner with our supplier to provide an extended warranty for our client.